How to use the concrete calculator
Choose a slab, footing or wall for anything rectangular, or a round column. Enter the length and width in meters or feet, and the thickness in millimeters, centimeters, meters, inches or feet. For a column, the length box is its height and the thickness box its diameter. Set the number of identical pieces, such as four columns.
Pick the concrete grade, your cement bag size and an allowance for waste. The result is the volume to order or mix, then the cement bags, sand, coarse aggregate and water for that mix.
How the materials are worked out
Volume is length × width × thickness, or π ÷ 4 × diameter² × height for a column, times the number of pieces, plus the waste allowance. That is the wet volume of finished concrete.
Loose cement, sand and aggregate take up more room than the concrete they make, because the fine particles and cement paste fill the gaps between stones. A common site rule multiplies the wet volume by 1.54 to get the dry volume of materials. The dry volume is split in the mix ratio, and cement is turned into kilograms at 1,440 kg/m³. Water is estimated at a water–cement ratio of 0.5.
IS 456 allows nominal mixes only for M20 and lower, and its Table 9 gives them by mass of aggregate per 50 kg of cement. The 1 : 3 : 6, 1 : 2 : 4 and 1 : 1.5 : 3 ratios used here are the volume batching ratios commonly used on site for M10, M15 and M20. M25 and above should be a design mix tested by a lab, so treat the M25 figures as a rough estimate.
Worked examples
A 4 m × 3 m slab, 10 cm thick, is 1.2 m³. With 5% extra that is 1.26 m³ (44.5 ft³ or 1.65 yd³). For M20 the dry volume is 1.26 × 1.54 = 1.94 m³, and one part in 5.5 is cement: about 508 kg, or 10.16 bags of 50 kg, so buy 11. It also needs 0.529 m³ of sand, 1.058 m³ of coarse aggregate and about 254 liters of water.
Four round columns, 30 cm across and 3 m high, hold 0.848 m³. With 5% extra that is 0.891 m³, needing 7.18 bags of cement, so 8 bags.
A 10 ft × 10 ft patio, 4 in thick, is 33.33 ft³ or 1.23 yd³. Mixed on site at 1 : 1.5 : 3 with no allowance for waste, it takes 8.93 US 94 lb bags of portland cement, so 9.
Ordering and mixing tips
The figures are estimates for planning and buying. Some practical points:
- Ready-mix suppliers sell by the cubic meter or cubic yard. Order the volume shown, which already includes your waste allowance.
- 5% extra suits a neat, formed slab. Use 10% or more for uneven ground or hand mixing.
- Wet sand bulks up and holds water. Measure it dry if you can, and add water slowly until the mix is workable.
- For structural work such as beams, suspended slabs and columns, follow the mix, cover and curing your engineer specifies.