Concrete to order

1.26 m³

44.5 ft³, 1.65 yd³. Includes 5% extra on 1.2 m³.

Cement bags (50 kg)

11

10.16 bags, 508 kg of cement. Dry volume 1.94 m³ (wet × 1.54) split 1 : 1.5 : 3, at 1440 kg/m³.

Sand (fine aggregate)

0.529 m³

18.69 ft³, 0.69 yd³.

Coarse aggregate (gravel)

1.058 m³

37.38 ft³, 1.38 yd³.

Water, about

254 liters

At a water–cement ratio of 0.5. Use the ratio your engineer specifies.

How to use the concrete calculator

Choose a slab, footing or wall for anything rectangular, or a round column. Enter the length and width in meters or feet, and the thickness in millimeters, centimeters, meters, inches or feet. For a column, the length box is its height and the thickness box its diameter. Set the number of identical pieces, such as four columns.

Pick the concrete grade, your cement bag size and an allowance for waste. The result is the volume to order or mix, then the cement bags, sand, coarse aggregate and water for that mix.

How the materials are worked out

Volume is length × width × thickness, or π ÷ 4 × diameter² × height for a column, times the number of pieces, plus the waste allowance. That is the wet volume of finished concrete.

Loose cement, sand and aggregate take up more room than the concrete they make, because the fine particles and cement paste fill the gaps between stones. A common site rule multiplies the wet volume by 1.54 to get the dry volume of materials. The dry volume is split in the mix ratio, and cement is turned into kilograms at 1,440 kg/m³. Water is estimated at a water–cement ratio of 0.5.

IS 456 allows nominal mixes only for M20 and lower, and its Table 9 gives them by mass of aggregate per 50 kg of cement. The 1 : 3 : 6, 1 : 2 : 4 and 1 : 1.5 : 3 ratios used here are the volume batching ratios commonly used on site for M10, M15 and M20. M25 and above should be a design mix tested by a lab, so treat the M25 figures as a rough estimate.

Worked examples

A 4 m × 3 m slab, 10 cm thick, is 1.2 m³. With 5% extra that is 1.26 m³ (44.5 ft³ or 1.65 yd³). For M20 the dry volume is 1.26 × 1.54 = 1.94 m³, and one part in 5.5 is cement: about 508 kg, or 10.16 bags of 50 kg, so buy 11. It also needs 0.529 m³ of sand, 1.058 m³ of coarse aggregate and about 254 liters of water.

Four round columns, 30 cm across and 3 m high, hold 0.848 m³. With 5% extra that is 0.891 m³, needing 7.18 bags of cement, so 8 bags.

A 10 ft × 10 ft patio, 4 in thick, is 33.33 ft³ or 1.23 yd³. Mixed on site at 1 : 1.5 : 3 with no allowance for waste, it takes 8.93 US 94 lb bags of portland cement, so 9.

Ordering and mixing tips

The figures are estimates for planning and buying. Some practical points:

  • Ready-mix suppliers sell by the cubic meter or cubic yard. Order the volume shown, which already includes your waste allowance.
  • 5% extra suits a neat, formed slab. Use 10% or more for uneven ground or hand mixing.
  • Wet sand bulks up and holds water. Measure it dry if you can, and add water slowly until the mix is workable.
  • For structural work such as beams, suspended slabs and columns, follow the mix, cover and curing your engineer specifies.

Sources

Frequently Asked Questions

How many bags of cement are needed for 1 m³ of M20 concrete?
About 8.06 bags of 50 kg: 1.54 m³ dry volume ÷ 5.5 parts = 0.28 m³ of cement, which is 403 kg at 1,440 kg/m³. Add your waste allowance on top.
How do I convert concrete from m³ to cubic yards?
Multiply cubic meters by 1.308, or divide cubic feet by 27. The calculator shows m³, ft³ and yd³ for every result.
Why multiply by 1.54 for dry volume?
The dry materials have air gaps between the particles. Once mixed with water, the sand fills the gaps between the stones and the cement fills the gaps in the sand, so the finished concrete takes up about 1 ÷ 1.54 of the loose volume.
What is the difference between M15 and M20 concrete?
The number is the characteristic compressive strength in N/mm² at 28 days. M20 is stronger and uses more cement: 1 : 1.5 : 3 against 1 : 2 : 4 by volume.
How thick should a concrete slab be?
About 75 to 100 mm (3 to 4 in) is common for paths and patios, and 100 to 150 mm (4 to 6 in) for driveways and ground floors. Suspended slabs and anything carrying heavy loads need an engineer's design.